The hypotenuse allowance (in m) for a 30 m long chain, if the slope is 1:10 is ..........
Try it first: pick an option, then read the explanation.
Understanding Hypotenusal Allowance
When you measure distance on sloping ground, the length measured along the slope (the hypotenuse) is always longer than the true horizontal distance. To get an accurate horizontal measurement for maps and plans, a correction must be applied.
Hypotenusal Allowance: It is the correction applied to the sloped distance to find the equivalent horizontal distance. Essentially, it's the extra length that needs to be measured along the slope to ensure the corresponding horizontal length is correct.
For a slope of 1 in 10, the calculation shows that for a 30-meter chain, you need to account for an additional 0.15 meters along the slope to get a true 30m horizontal distance.
Detailed Analysis of the Calculation
Here is the step-by-step calculation to determine the hypotenusal allowance:

Calculation Steps:
Given:
- Chain Length = 30 m (which is equal to 150 links, as 1 link = 0.2 m).
- Slope = 1 in 10.
The formula for hypotenusal allowance in links is given by:
Allowance = 150 (sec φ - 1) links
Where φ is the angle of the slope.
From the slope, tan φ = 1/10, which gives φ ≈ 5.71°.
Calculating sec φ:
sec(5.71°) ≈ 1.00498
Substitute this value into the formula:
Allowance = 150 (1.00498 - 1) = 150 × 0.00498 = 0.747 links
Finally, convert the allowance from links back to meters:
Allowance in meters = 0.747 links × 0.2 m/link ≈ 0.15 m
Study Tips
- Slope Means Correction: Always remember that any measurement on a slope needs correction to find the true horizontal distance for accurate mapping.
- Concept Over Formula: While the formula is useful, understanding the concept is key. You are finding the difference between the hypotenuse (sloped length) and the base (horizontal length) of a right-angled triangle.
- Practical Application: This correction is critical in chain surveying to avoid significant errors in distance measurement, which would affect the entire survey's accuracy.