Surveying·MCQ explained

In a chain surveying work of a traverse, it is necessary to apply the correction due to sag for the tape. The correction is:

Try it first: pick an option, then read the explanation.

Correct answer: A. always negative
Home >MCQ >Surveying MCQs >MCQs on Chain Surveying (6)

Core Concept: Understanding Sag

When a survey tape or chain is stretched between two supports, it does not form a perfectly straight line. Due to its own weight, it hangs downwards in a curve known as a catenary. This means the actual measured length along the curved tape is always longer than the true, straight-line horizontal distance between the two support points.

Because the measured distance is always too long, this introduces a positive error into the measurement. To get the correct distance, a correction must be applied, and this correction must therefore be always negative (subtractive).

Formula for Sag Correction

The magnitude of the sag correction ( \(C_s\) ) depends on the weight of the tape, the length of the span, and the tension applied. The formula is:

$$ C_s = \frac{w^2 L^3}{24 P^2} = \frac{W^2 L}{24 P^2} $$

  • \(C_s\) = The sag correction (always negative)
  • \(L\) = The length of the tape suspended between supports
  • \(P\) = The pull or tension applied to the tape
  • \(w\) = The weight of the tape per unit length
  • \(W\) = The total weight of the tape between the supports (W = wL)

As you can see from the physics, sag will always occur unless the tape is fully supported, so the correction will always be required and will always be negative.

Summary of Errors and Corrections

It's helpful to remember the nature of different errors in chain surveying:

Error SourceError SignCorrection Sign
SaggingAlways Positive (+)Always Negative (-)
SlopeAlways Positive (+)Always Negative (-)
Wrong AlignmentAlways Positive (+)Always Negative (-)
StandardizationPositive or NegativeNegative or Positive
TemperaturePositive or NegativeNegative or Positive
Pull (Tension)Positive or NegativeNegative or Positive
Home >MCQ >Surveying MCQs >MCQs on Chain Surveying (6)