Lime–Cement Plaster Ratio 1:1:6

In mixed-binder plaster, the standard order of the ratio is cement : lime : sand. So for 1:1:6 plaster: 1 part cement, 1 part lime, and 6 parts sand.

Cement provides early strength and sets quickly; lime adds plasticity and workability and reduces cracking by its slow carbonation. Together they balance workability and early strength in a way neither binder achieves alone.

Cement : lime : sand — option B.

Key takeaway

Plaster ratios are written cement : lime : sand — always cement first in the convention.