The initial setting time of fresh concrete should be:

Try it first: pick an option, then read the explanation.

Correct answer: B. Greater than 30 minutes

⏱ Initial Setting Time of Concrete

The initial setting time is the time at which the concrete starts to lose workability and can no longer be properly placed, compacted, or finished. IS 456:2000 and IS 8112 require that the initial setting time of cement (and concrete made from it) must be not less than 30 minutes. This gives the construction team enough time to mix, transport, place, and compact before the paste stiffens.

The final setting time should not exceed 600 minutes (10 hours).

Initial setting time must be greater than 30 minutes — option B.

Key takeaway

Initial setting: ≥ 30 min. Final setting: ≤ 600 min. These are the two key time limits to remember.