Detailed Explanation: Estimating Water Quantity in Concrete

Water in concrete serves two distinct functions: (1) it hydrates the cement to form the binding C-S-H gel, and (2) it coats and lubricates the aggregate particles to give workability. The empirical formula for estimating total water content combines these two requirements.

Why C is correct: The approximate water requirement is:
• 30% of cement weight: The theoretical water needed for complete hydration of cement (w/c for complete hydration ≈ 0.25–0.30). For a typical cement content of ~300–400 kg/m³, this adds 90–120 litres.
• 5% of aggregate weight: Water needed to wet the large aggregate surface area and make the mix workable. With ~1700 kg/m³ total aggregate, this adds ~85 litres.
Total: ~175–205 litres/m³, consistent with typical concrete mix designs.
Option D (5% cement + 30% aggregate) would give ~15 + 510 = 525 litres — far too much water for any structural concrete.

Water Content Calculation Example

ComponentTypical Qty (per m³)Water Contribution
Cement350 kg30% × 350 = 105 litres
Aggregate (FA+CA)1700 kg5% × 1700 = 85 litres
Total water~190 litres/m³

Key Concepts for Students

  • This is an empirical estimate; actual water content varies with aggregate size, workability, and admixtures.
  • The minimum water for complete hydration is w/c = 0.23 — any less and hydration is incomplete; any more adds porosity.
  • In IS 10262 mix design, actual water content is determined from tables based on maximum aggregate size and slump requirements.