Engineering Materials·MCQ explained

In the process of hydration of OPC, to complete all chemical reaction, the water requirement (expressed as the percentage of cement) is ........

Try it first: pick an option, then read the explanation.

Correct answer: D. 35 to 45%

Detailed Explanation: Water Requirement for Complete OPC Hydration

This question expresses the same concept as Q8 but in percentage terms rather than w/c ratio. Both are different ways of stating the same physical requirement.

Why D (35 to 45%) is correct: The total water needed for complete hydration of OPC = 35% to 45% of cement mass = w/c ratio of 0.35 to 0.45. Breakdown:
• Non-evaporable (chemically combined) water: ~23% of cement mass (w/c = 0.23)
• Gel water (adsorbed in C-S-H): ~12–22% of cement mass
• Total: ~35–45%
Options A (5–8%) and B (8–16%) are only sufficient for early reactions, not complete hydration. Option C (20–25%) covers chemical water but not gel water.

Water Requirements for OPC Hydration

Water Type% of Cement MassW/C Equivalent
Non-evaporable (chemical)~23%~0.23
Gel water~12–22%~0.12–0.22
Total (complete hydration)35–45%0.35–0.45

Key Concepts for Students

  • 35–45% of cement mass = w/c 0.35–0.45 — required for complete hydration.
  • Practical w/c is typically 0.40–0.55 to balance complete hydration + workability + strength.