Engineering Materials·MCQ explained

The process of hardening concrete by keeping its surface moist is known as:

Try it first: pick an option, then read the explanation.

Correct answer: C. Curing

Detailed Explanation: Curing — Keeping Concrete Moist for Hardening

Why C (Curing) is correct: Keeping the concrete surface moist so that hydration can continue and the concrete can reach its design strength is precisely the definition of curing. This is a deliberate, controlled process governed by IS 456 minimum duration requirements.

Distinguishing Similar Terms

TermDefinitionIS Reference
PlacingDepositing fresh concrete in formwork at the correct locationIS 456 Cl. 13
WettingGeneral application of water (not a technical concrete term)—
CuringMaintaining moisture and temperature for concrete to develop design strengthIS 456 Cl. 13.5
CompactingRemoving entrapped air to densify fresh concreteIS 456 Cl. 13.3

Minimum Curing Durations (IS 456:2000)

ConditionMinimum Curing Period
OPC concrete (M20 and below)7 days
OPC concrete (above M20)14 days
Blended cement (PPC/PSC)14–28 days
Hot weather (>40°C)Up to 28 days
  • Curing = process of keeping concrete moist for hardening and full strength development.
  • Start curing within 10 hours of placement to prevent early surface drying.
  • Minimum 7 days for OPC (IS 456); longer for blended cements and hot weather.