What is the minimum period before striking the formwork to RCC slabs (with props to be refixed immediately after removal of formwork)?

What is the minimum period before striking the formwork to RCC slabs (with props to be refixed immediately after removal of formwork)?

A. 3 days
B. 14 days
C. 7 days
D. 21 days
Correct Answer: A. 3 days

📚 Detailed Explanation: Soffit Formwork to Slabs — Minimum 3 Days

Why A (3 days) is correct: IS 456:2000 specifies that soffit formwork (bottom shuttering) to slabs can be removed after just 3 days, provided the props are refixed immediately. Slabs are thinner and more uniformly loaded than beams, and by 3 days OPC concrete has sufficient early strength to span between the re-erected props without cracking.

IS 456:2000 Formwork Stripping Times

S.No. Type of Formwork OPC (Minimum Period) RHC (Minimum Period)
1 Vertical formwork to columns, walls, beams 16–24 hours 12 hours
2 Soffit formwork to slabs (props refixed immediately) 3 days 2 days
3 Soffit formwork to beams (props refixed immediately) 7 days 5 days
4a Props to slabs: spanning up to 4.5 m 7 days 5 days
4b Props to slabs: spanning over 4.5 m 14 days 10 days
5a Props to beams and arches: spanning up to 6 m 14 days 10 days
5b Props to beams and arches: spanning over 6 m 21 days 14 days

Key Distinction: Slab vs. Beam Soffit Formwork

Member Min. Stripping Time (OPC) Reason
Slab soffit 3 days Thinner section, lower self-weight, shorter span between props
Beam soffit 7 days Heavier section, greater span, needs more strength development
  • Condition: props must be refixed immediately after removing formwork. If props are not refixed, the slab must carry its own weight unsupported — a different (longer) duration applies.
  • 3 days applies to OPC; Rapid Hardening Cement allows removal after just 2 days.