Engineering Materials·MCQ explained

What is the minimum period before striking the formwork to RCC slabs (with props to be refixed immediately after removal of formwork)?

Try it first: pick an option, then read the explanation.

Correct answer: A. 3 days

Detailed Explanation: Soffit Formwork to Slabs — Minimum 3 Days

Why A (3 days) is correct: IS 456:2000 specifies that soffit formwork (bottom shuttering) to slabs can be removed after just 3 days, provided the props are refixed immediately. Slabs are thinner and more uniformly loaded than beams, and by 3 days OPC concrete has sufficient early strength to span between the re-erected props without cracking.

IS 456:2000 Formwork Stripping Times

S.No.Type of FormworkOPC (Minimum Period)RHC (Minimum Period)
1Vertical formwork to columns, walls, beams16–24 hours12 hours
2Soffit formwork to slabs (props refixed immediately)3 days2 days
3Soffit formwork to beams (props refixed immediately)7 days5 days
4aProps to slabs: spanning up to 4.5 m7 days5 days
4bProps to slabs: spanning over 4.5 m14 days10 days
5aProps to beams and arches: spanning up to 6 m14 days10 days
5bProps to beams and arches: spanning over 6 m21 days14 days

Key Distinction: Slab vs. Beam Soffit Formwork

MemberMin. Stripping Time (OPC)Reason
Slab soffit3 daysThinner section, lower self-weight, shorter span between props
Beam soffit7 daysHeavier section, greater span, needs more strength development
  • Condition: props must be refixed immediately after removing formwork. If props are not refixed, the slab must carry its own weight unsupported — a different (longer) duration applies.
  • 3 days applies to OPC; Rapid Hardening Cement allows removal after just 2 days.