The shuttering (props) of a hall measuring 4 m × 5 m can be removed after:

Try it first: pick an option, then read the explanation.

Correct answer: B. 7 days

Detailed Explanation: Hall 4 m × 5 m — Prop Removal After 7 Days

Why B (7 days) is correct: For two-way slabs, the governing (shorter) span determines the structural behaviour. The shorter span here is 4 m, which falls in the “spanning up to 4.5 m” category in IS 456:2000. Therefore props can be removed after 7 days.

How to Identify the Governing Span

Hall DimensionShorter SpanIS 456 CategoryMin. Period
4 m × 5 m4 m (< 4.5 m)Props to slabs: up to 4.5 m7 days
5 m × 6 m (example)5 m (> 4.5 m)Props to slabs: over 4.5 m14 days

IS 456:2000 Prop Removal for Slabs

S.No.Type of FormworkOPC (Minimum Period)RHC (Minimum Period)
1Vertical formwork to columns, walls, beams16–24 hours12 hours
2Soffit formwork to slabs (props refixed immediately)3 days2 days
3Soffit formwork to beams (props refixed immediately)7 days5 days
4aProps to slabs: spanning up to 4.5 m7 days5 days
4bProps to slabs: spanning over 4.5 m14 days10 days
5aProps to beams and arches: spanning up to 6 m14 days10 days
5bProps to beams and arches: spanning over 6 m21 days14 days
  • For a 4 m × 5 m slab, shorter span = 4 m < 4.5 m → props removable after 7 days.
  • Had the shorter span been just 0.5 m more (4.5–5 m), the minimum would jump to 14 days.
  • The 5 m (longer) span does NOT govern — shorter span controls for two-way slabs.