Engineering Materials·MCQ explained

Which of the following types of joints is a temporary joint left between subsequent concreting operations?

Try it first: pick an option, then read the explanation.

Correct answer: B. Construction joint

Detailed Explanation: Construction Joint is the Temporary Joint Between Successive Pours

Why B (Construction joint) is correct: A construction joint is the interface formed when fresh concrete is placed against concrete that has already hardened or partially set. It arises whenever concreting work is deliberately or unavoidably halted — at the end of a working day, due to equipment failure, or between planned lifts of a large structure. It is a temporary joint in the sense that it is not pre-designed to allow movement; rather, it is a consequence of the construction sequence.

The Four Main Types of Joints in Concrete Works

Joint TypePurposeDesigned / Temporary?Allows Movement?
B. Construction JointInterface between successive concreting operations; work stoppage jointTemporary (unplanned or planned work-stoppage)No — monolithic behaviour intended
A. Isolation JointSeparates a structure from adjacent structures or foundations to prevent stress transferDesigned (planned)Yes — vertical movement; allows differential settlement
C. Contraction JointControls and localises shrinkage cracking in slabs and pavementsDesigned (planned)Partial — groove or weakened plane allows controlled crack
D. Expansion JointAccommodates thermal expansion/contraction of long or large structuresDesigned (planned)Yes — full gap with compressible filler

Construction Joint Details

AspectDetail
Location (beams/slabs)Within the middle third of the span — where shear force and bending moment are minimum
Location (columns)Horizontally, 10–15 cm below the junction with a beam or haunch
Surface preparationOld concrete surface must be roughened (wire brushing / chipping), cleaned, and moistened before placing new concrete; bond coat of cement slurry may be applied
Direction in slabsPerpendicular to the main reinforcement; reinforcement continues across the joint unbroken
Key requirement (IS 456)Joint surface must be free of laitance; roughened to expose aggregate; shear key or rebars ensure load transfer
  • Construction joint = temporary interface formed when concreting is stopped and restarted.
  • Located at positions of minimum shear force and bending moment (middle third of span in beams/slabs).
  • Surface must be roughened, cleaned, and wetted before resuming concreting to ensure bond.