Maximum shrinkage in concrete occurs after drying for:

Try it first: pick an option, then read the explanation.

Correct answer: A. 28 days

Detailed Explanation: Maximum (Rate of) Shrinkage Occurs by 28 Days

Why A (28 days) is correct: The initial rapid phase of drying shrinkage occurs in the first 28 days of drying. During this period, most of the free capillary water evaporates from the concrete, causing the largest volume reduction. After 28 days, the remaining adsorbed and gel water evaporates much more slowly, and further shrinkage is minor.

Drying Shrinkage Progression

Drying DurationApproximate Cumulative ShrinkageWhat's Happening
3 days≈ 5–10% of ultimateSurface water evaporating; thin surface layer drying
7 days≈ 10–20% of ultimateDrying penetrating deeper; rapid evaporation continues
28 days≈ 14–34% of ultimateMost free capillary water evaporated; maximum rate phase ending
3 months≈ 40–70% of ultimateAdsorbed water evaporating; slower rate
1 year≈ 75–90% of ultimateGel water loss; very slow; hygrothermal cycling
Several years≈ 100% (ultimate reached)Equilibrium with ambient conditions

Factors That Affect How Quickly 28-day Shrinkage Completes

FactorFaster ShrinkageSlower Shrinkage
Ambient humidityLow RH (<50%)High RH (>80%)
TemperatureHigh temperature → faster evaporationLow temperature → slower evaporation
Member thicknessThin members dry faster (high surface/volume ratio)Thick members dry slowly (water diffuses from core)
w/c ratioHigh w/c → more water to evaporate soonerLow w/c → less free water; more is bound
  • The maximum rate of shrinkage occurs in the first 28 days of drying when free capillary water evaporates.
  • IS 456:2000 design shrinkage strain = 0.0003 (total, not just 28-day).
  • Shrinkage movement joints in large concrete structures are essential to accommodate this deformation.