Engineering Materials·MCQ explained

Identify the correct methods of surface preparation used for joining old and new concrete to each other: (i) Sandblasting (ii) Chipping (iii) Removal of surface by grinding

Try it first: pick an option, then read the explanation.

Correct answer: B. All of i, ii and iii

Detailed Explanation: Surface Preparation for Old-New Concrete Bond

Why B (All three) is correct: When new concrete is cast against hardened old concrete (construction joints, repairs, overlays), the contact surface must be prepared to:
1. Remove weak laitance (milky surface layer of fine particles)
2. Expose aggregate for mechanical bond
3. Create sufficient surface roughness for interlocking
All three methods achieve these objectives.

Surface Preparation Methods

MethodHow It WorksBest For
(i) SandblastingHigh-velocity sand particles abrade surface, remove laitanceLarge flat surfaces, bridge decks
(ii) ChippingPneumatic hammer/chisel chips surface to expose aggregateConstruction joints, columns
(iii) GrindingDiamond/abrasive wheel removes surface layer uniformlyFloor joints, slabs

Additional Requirements for Bonding Old to New Concrete

  • After surface preparation: clean the surface with water and keep it damp (SSD condition) before casting new concrete.
  • Apply bonding agent (cement slurry or epoxy-based) on the prepared surface just before casting new concrete.
  • IS 456 specifies that construction joints must have the laitance removed to ensure proper bond.