Water required per bag of cement is:

Water required per bag of cement (50 kg) for a standard concrete mix is approximately:

A. 7 kg
B. 14 kg
C. 28 kg
D. 35 kg
Correct Answer: C. 28 kg

📚 Detailed Explanation: Water Per Bag of Cement

Why C (28 kg) is correct: For a 1:2:4 nominal mix (M15), the typical design water-cement ratio is approximately 0.55–0.60. Taking w/c = 0.56 as the reference value:
Water = w/c × cement = 0.56 × 50 kg = 28 kg per bag
w/c ratio for 1:2:4 mix ≈ 0.55–0.60
Using w/c = 0.56 (standard reference):

Water = 0.56 × 50 kg = 28 kg per bag

Water Requirement vs. Mix Ratio

Nominal Mix Approx. w/c Water per 50 kg Bag (kg)
1:3:6 (M10) 0.65–0.70 33–35 kg
1:2:4 (M15) 0.55–0.60 28–30 kg
1:1.5:3 (M20) 0.50–0.55 25–28 kg
1:1:2 (M25) 0.45–0.50 22–25 kg
  • Standard water requirement: 28 kg per 50 kg bag of cement for 1:2:4 (M15) mix.