Surveying·MCQ explained

_____ is the method of locating an offset point from 2 different points on a chain line in such a way that all the three points form a near-equilateral triangle.

Try it first: pick an option, then read the explanation.

Correct answer: A. Method of ties

Detailed Explanation: The Method of Ties

While most of this question set covers circular and transition curve geometry, this question (and Q3) addresses chain-survey detail-location technique, since both topics share the common theme of linear (tape-only) field methods used alongside curve setting work.

Why "Method of ties" is correct:
The method of ties locates a detail point by measuring two linear distances ("ties") from that point to two different, known points on the chain line. For best accuracy, these two tie measurements (together with the known distance between the two chain-line points) should form a triangle as close to equilateral as possible — this geometry minimises the sensitivity of the plotted point's position to small measurement errors in the ties, giving the most reliable fix.

Comparison of Offset/Tie Methods

MethodHow the point is locatedBest suited for
Method of tiesTwo tie distances from two chain-line points, forming a near-equilateral triangleImportant or irregular detail points needing high positional accuracy
Perpendicular offset methodA single perpendicular distance from one chain-line pointPoints close to the chain line, fast routine detailing
Oblique offset methodA single offset measured at any convenient angle (not necessarily 90°) from a chain-line pointPoints where a perpendicular cannot easily be set out
Swing offset methodThe offset distance is found by swinging the tape (arc) from a chain-line point until it is minimum (i.e., perpendicular)Locating points without needing a separate right-angle instrument

Why the Other Options Are Wrong

B — Swing offset method: This uses a single swung tape measurement to find the perpendicular offset from one point, not two ties from two different points forming a triangle.

C — Oblique offset method: This uses a single offset at a convenient (non-perpendicular) angle from one chain-line point — again, not the two-point tie technique described.

D — Perpendicular offset method: This uses a single perpendicular measurement from one chain-line point to the detail, the simplest and most common offset technique, but distinctly different from the two-tie, triangle-forming method described in the question.

Key Concepts for Students

  • Near-equilateral triangle = best accuracy: When the triangle formed by the two tie lengths and the base (chain-line segment between the two reference points) is close to equilateral, a small error in either tie length causes the smallest possible shift in the plotted point's position — this geometric principle is the core reason the method of ties is preferred for accuracy-sensitive points.
  • Method of ties needs no right-angle instrument: Unlike the perpendicular offset method (which technically requires some means of judging a right angle), the method of ties relies purely on two straightforward linear tape measurements, making it valuable when an optical square or cross staff is unavailable.
  • Use for critical detail points: Because of its accuracy advantage, the method of ties is typically reserved for locating important features (building corners, boundary points) rather than routine, less critical detail, where a faster perpendicular or oblique offset suffices.