Surveying·MCQ explained

Which of the following options represents an INCORRECT relation between the fundamental axes of a theodolite?

Try it first: pick an option, then read the explanation.

Correct answer: C. The axis of the striding level must be perpendicular to the transit axis

Detailed Explanation: The Striding Level–Trunnion Axis Relationship

This question continues testing the fundamental axis relationships of a theodolite, this time focusing specifically on the striding level — an accessory bubble used to check whether the horizontal (trunnion) axis is truly horizontal.

Why "perpendicular" is the incorrect relation here:
The striding level is a long, sensitive bubble tube placed (straddling, hence "striding") directly across the trunnion axis, resting on its bearings at each end. For this bubble to correctly indicate whether the trunnion axis is horizontal, its own bubble axis must be parallel to the trunnion (transit/horizontal) axis it is checking — not perpendicular. If it were perpendicular, centring the bubble would tell you nothing about the levelness of the trunnion axis itself.

Verifying the Other Three Relations (All Correct)

StatementStatusWhy
A — Altitude level axis parallel to line of collimationCorrectCentring the altitude bubble must make the line of sight exactly horizontal — this requires their axes to be parallel.
B — Plate level axis perpendicular to vertical axisCorrectCentring the plate bubble (rotated through 180° in two perpendicular positions) confirms the vertical axis is vertical, which requires this perpendicular relationship.
D — Trunnion axis perpendicular to line of sightCorrectThis (more precisely, line of collimation perpendicular to the horizontal/trunnion axis) ensures the telescope sweeps a true vertical plane and there is no horizontal collimation error.

Key Concepts for Students

  • Striding level checks the trunnion axis, parallel is the rule: Any accessory level used to check a particular axis must have its own bubble axis parallel to that axis — this is true for the striding level (checks trunnion/horizontal axis) and the altitude level (checks the line of collimation).
  • Perpendicular relationships apply between DIFFERENT axes: Perpendicular relationships in theodolite geometry (plate level vs. vertical axis; trunnion axis vs. vertical axis; line of collimation vs. trunnion axis) always relate two genuinely different axes, never a level checking its own reference axis.
  • Spire test connection: The striding level is specifically used in the Spire test, which verifies that the horizontal/trunnion axis is perpendicular to the vertical axis — a separate but related check covered in Q38.