Geotechnical·MCQ explained

In a falling head test, the initial head level is 100 cm and the head level after 100 seconds is 10 cm. The area of cross-section of stand-pipe is 10 cm², and the area of cross-section of soil sample is 100 cm². Find the permeability of soil sample if the length of sample is 20 cm.

Try it first: pick an option, then read the explanation.

Correct answer: D. 0.046 cm/s

Detailed Explanation

The falling head test is used specifically for low-permeability soils (see Q5), where a constant-head setup would produce an immeasurably slow, hard-to-read flow rate. Instead, it tracks how quickly the water level in a narrow stand-pipe falls over a measured time interval.

Given: area of stand-pipe a = 10 cm²; area of soil sample A = 100 cm²; length of sample L = 20 cm; time t = 100 sec; initial head h1 = 100 cm; final head h2 = 10 cm.

Formula: K = 2.303 · (a·L)/(A·t) · log10(h1/h2)

K = 2.303 × (10 × 20)/(100 × 100) × log₁₀(100/10) = 2.303 × 0.02 × 1 = 0.04606 cm/s

Why "0.046 cm/s" Is Correct

Substituting all given values into the falling-head formula gives K ≈ 0.04606 cm/s, which rounds to 0.046 cm/s.

FALLING HEAD TESTh₁ (start)h₂ (end, t)stand-pipearea aSoil SampleLength L, Area Aoutflow

Water level in the narrow stand-pipe (area a) falls from h1 to h2 over time t, driving flow through the soil sample (area A, length L). K = 2.303(aL/At)·log10(h1/h2).

Why the Other Options Are Wrong

  • 4.6 cm/s: off by a factor of 100 — a likely decimal-point error in converting or combining the area ratio (a·L)/(A·t).
  • 2.3 cm/s: close to the constant 2.303 itself, suggesting this distractor comes from forgetting to multiply by the (a·L)/(A·t) factor entirely.
  • 0.023 cm/s: roughly half the correct value — could result from a factor-of-2 slip somewhere in the area or length terms.

Key Point

The falling-head formula's log₁₀(h1/h2) term uses base-10 log with the 2.303 conversion factor built in (2.303 ≈ ln(10)) — using natural log directly without this factor would give a very different (wrong) result.

Key Concepts for Students

  • log₁₀(100/10) = log₁₀(10) = 1 exactly — a clean number that simplifies this particular calculation nicely.
  • The stand-pipe area (a) is deliberately much smaller than the soil sample area (A), so that even a slow flow rate produces a clearly measurable, relatively quick drop in the narrow stand-pipe's water level.
  • See Q22 and Q24 for two more fully worked falling-head calculations using this exact same formula.
  • See Q5 for why the falling head method specifically suits low-permeability soils like silt and clay, in contrast to the constant head method used for sand and gravel.

Going Deeper: Falling Head vs. Constant Head: Full Comparison

These are the two standard laboratory methods for determining K, and choosing between them correctly is tested repeatedly throughout this topic (Q5, Q9, Q15, Q18).

MethodFormulaBest Suited For
Constant headK = QL/(Aht)High-permeability soils (gravel, sand) — flow rate is large enough to measure directly and steadily
Falling (variable) headK = 2.303(aL/At)·log10(h1/h2)Low-permeability soils (silt, clay) — flow is too slow to measure as a steady rate, but a measurable head drop still accumulates over time

Both formulas share the same core structure — a geometry factor (areas and length) multiplied by a driving-head term — but the falling head formula additionally accounts for the head itself continuously changing during the test, which is why it needs the logarithmic h1/h2 term rather than a single constant h.