Low workability of concrete conforms to a slump of:

Low workability of concrete conforms to a slump of:

A. 25-75 mm
B. 50-100 mm
C. 75-100 mm
D. 100-150 mm
Correct Answer: A. 25-75 mm

📚 Detailed Explanation: Slump Range for Low Workability

Why A (25–75 mm) is correct: IS 456 / standard textbook classification:
• 0–25 mm: Very low workability
25–75 mm: Low workability
• 50–100 mm: Medium workability
• 75–150 mm: High workability
Options B (50–100) and C (75–100) fall in the medium range. Option D (100–150) is high workability. The correct low workability range is 25–75 mm.

Workability Classification by Slump

Workability Slump (mm) Typical Use
Very low 0–25 Mass concrete, pavement (manual)
Low 25–75 Road slabs, lightly reinforced members
Medium 50–100 Normal RCC beams, slabs, columns
High 75–150 Heavily reinforced, pumped concrete
  • Low workability = 25–75 mm slump per IS 456.