In the concrete mix with proportions of its ingredient 1:3:6, the actual quantity of sand per unit volume of cement, if bulking of the sand is 15% is …….. .

In a 1:3:6 concrete mix, the actual quantity of sand per unit volume of cement, if bulking of sand is 15%, is:

A. 3
B. 3.45
C. 6
D. 4.5
Correct Answer: B. 3.45

📚 Detailed Explanation: Bulking Correction for 1:3:6 Mix

Why B (3.45) is correct: The mix specifies 3 parts dry sand per 1 part cement. With 15% bulking, the moist sand occupies more volume. To deliver 3 dry-volume units of sand, we must measure an increased (bulked) volume.
Specified dry sand per unit cement = 3 volumes
Bulking = 15% = 0.15

Measured moist sand volume = 3 × (1 + 0.15)
= 3 × 1.15 = 3.45 volumes

General Bulking Correction Table

Mix Specified Sand Bulking Measured Volume
1:2:4 2 20% 2 × 1.20 = 2.40
1:3:6 3 15% 3 × 1.15 = 3.45
1:1.5:3 1.5 25% 1.5 × 1.25 = 1.875
  • For 1:3:6 with 15% bulking: measure 3.45 volumes of moist sand per unit cement.