Construction joints are provided:

Construction joints in concrete structures are provided:

A. Where B.M. and S.F. are small
B. Where the member is supported by other member
C. At 18 m apart in huge structures
D. All of the above
Correct Answer: D. All of the above

📚 Detailed Explanation: Construction Joints Satisfy All Three Listed Conditions

Why D (All options are correct) is correct: This question tests comprehensive knowledge of construction joint requirements. All three conditions — minimum BM and SF, at member support junctions, and maximum 18 m spacing in huge structures — are standard requirements for construction joints per IS 456:2000 and general practice. (This question is closely related to Q5; both emphasise the multi-condition nature of construction joint placement.)

Verification of Each Condition

Condition Standard / Source Correct?
A. Where BM and SF are small IS 456:2000 Clause 13.3; middle third of simply supported span satisfies this for beams and slabs ✓ TRUE
B. Where member is supported by another member Support junctions (beam-column, slab-beam) are natural joint locations; load path transitions here; joint placement supported by IS 456 commentary ✓ TRUE
C. At 18 m intervals in huge structures IS 456:2000 and ACI 224R: for massive structures (dams, large mat foundations, mass retaining walls), construction joints at intervals not exceeding 18 m to control heat of hydration and pour volume ✓ TRUE

The 18 m Rule for Huge Structures

Why 18 m Maximum? Explanation
Heat of hydration control Large continuous pours generate significant heat; joints limit pour volume and allow heat dissipation between lifts
Shrinkage crack control Restraint-induced shrinkage cracking is proportional to the restrained length; limiting to 18 m reduces crack width
Logistics and quality Smaller pours are easier to place and compact uniformly; risk of cold joints within a pour is reduced
Standard reference IS 456:2000 Clause 13.3; ACI 207.1R for mass concrete
  • Construction joints: where BM and SF are small + where member is supported by another member + 18 m maximum spacing in huge structures.
  • All three conditions apply simultaneously; they are not alternatives but complementary criteria.
  • The 18 m rule applies to massive structures (dams, raft slabs, large walls); typical building elements follow the span-based rule.

← Back to MCQs on Joints in Concrete Works

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top