MCQs on Joints in Concrete Works

MCQs on Joints in Concrete Works

Questions 1–12 — Tap an option to check your answer.

Q1: Which type of joint is a temporary joint left between subsequent concreting operations?

Difficulty: Easy

A. Isolation joint
B. Construction joint
C. Contraction joint
D. Expansion joint
Detailed Explanation

Q2: Interval for expansion and contraction joints in India for smooth interface laid in winter?

Difficulty: Hard

A. 80 to 90 metres
B. 50 to 60 metres
C. 90 to 120 metres
D. 120 to 140 metres
Detailed Explanation

Q3: In expansion joints, loads are transferred through:

Difficulty: Medium

A. Aggregates
B. Dowel bars
C. Longitudinal bars
D. Tie bars
Detailed Explanation

Q4: Horizontal construction joints in concrete walls are generally provided at:

Difficulty: Easy

A. Window sill level
B. Soffit level
C. Floor level
D. All of the above
Detailed Explanation

Q5: A construction joint is provided where:

Difficulty: Easy

A. Bending moment is small
B. Shear force is small
C. The member is supported by another member
D. All of the above
Detailed Explanation

Q6: The surface where two successive placements of concrete meet is known as:

Difficulty: Easy

A. Contraction joint
B. Expansion joint
C. Construction joint
D. Both contraction joint and expansion joint
Detailed Explanation

Q7: Expansion joints are provided if the length of concrete structures exceeds:

Difficulty: Medium

A. 10 m
B. 15 m
C. 25 m
D. 45 m
Detailed Explanation

Q8: Pick up the correct statement about construction joint placement:

Difficulty: Medium

A. Construction joints in columns are provided a few cm below junction of beam
B. Construction joints in columns are provided at the bottom haunching
C. Construction joints in beams and slabs are within middle third of span
D. All of the above
Detailed Explanation

Q9: Construction joints are provided:

Difficulty: Easy

A. Where B.M. and S.F. are small
B. Where the member is supported by other member
C. At 18 m apart in huge structures
D. All of the above
Detailed Explanation

Q10: Pick up the correct statement about joints in concrete:

Difficulty: Easy

A. Construction joints are necessarily planned for their locations
B. Expansion joints are provided to accommodate thermal expansion
C. Construction joints are provided to control shrinkage cracks
D. All of the above
Detailed Explanation

Q11: According to IS 456-1978, expansion joints:

Difficulty: Medium

A. Are provided where plane changes abruptly
B. Are provided to ensure minimum resistance to movement
C. Are supported on separate columns
D. All of the above
Detailed Explanation

Q12: The construction joints in cement concrete:

Difficulty: Medium

A. Should be located where shear force is large
B. Should not be provided at corners
C. Should be located where bending moment is large
D. Should be spaced at 3 m apart in huge structures
Detailed Explanation

Scroll to Top