MCQs on Form Work

Questions 1–6 — Tap an option to check your answer.

Q1: The minimum stripping time of soffit formwork to beams (props to be refixed immediately after removal of formwork) is:

Difficulty: Easy

A. 3 days
B. 7 days
C. 14 days
D. 21 days
Detailed Explanation

Q2: What is the minimum period before striking the formwork to RCC slabs (with props to be refixed immediately after removal of formwork)?

Difficulty: Easy

A. 3 days
B. 14 days
C. 7 days
D. 21 days
Detailed Explanation

Q3: Under normal conditions using an ordinary cement the period of removal of the form work is:

Difficulty: Medium

A. 7 days for beam soffits
B. 14 days for bottom slabs of spans 4.6 m and more
C. 21 days for bottom beams over 6 m spans
D. All options are correct
Detailed Explanation

Q4: The shuttering of a hall measuring 4 m x 5 m, can be removed after:

Difficulty: Medium

A. 5 days
B. 7 days
C. 10 days
D. 14 days
Detailed Explanation

Q5: For walls, columns and vertical faces of all the structural members, the form work is generally removed after:

Difficulty: Easy

A. 24 to 48 hours
B. 3 days
C. 7 days
D. 14 days
Detailed Explanation

Q6: Concrete is generally placed on a:

Difficulty: Easy

A. Form work
B. Stand
C. Mould
D. Platform
Detailed Explanation