Engineering Materials·MCQ explained

The minimum stripping time of soffit formwork to beams (props to be refixed immediately after removal of formwork) is:

Try it first: pick an option, then read the explanation.

Correct answer: B. 7 days

Detailed Explanation: Soffit Formwork to Beams — Minimum Stripping Time

Why B (7 days) is correct: IS 456:2000 Table 1 specifies minimum periods for striking formwork. Beams carry significantly greater loads than slabs, so their soffit formwork (bottom shuttering) must stay in place longer to allow the concrete to gain sufficient strength before the weight of the beam transfers to it. With ordinary Portland cement, the minimum is 7 days.

IS 456:2000 Formwork Stripping Times (Full Table)

S.No.Type of FormworkOPC (Minimum Period)RHC (Minimum Period)
1Vertical formwork to columns, walls, beams16–24 hours12 hours
2Soffit formwork to slabs (props refixed immediately)3 days2 days
3Soffit formwork to beams (props refixed immediately)7 days5 days
4aProps to slabs: spanning up to 4.5 m7 days5 days
4bProps to slabs: spanning over 4.5 m14 days10 days
5aProps to beams and arches: spanning up to 6 m14 days10 days
5bProps to beams and arches: spanning over 6 m21 days14 days

Why 7 Days for Beam Soffits?

By 7 days, OPC concrete reaches approximately 65–70% of its 28-day characteristic strength — enough to carry its own weight and the newly refixed props without excessive deflection or cracking. Removing it earlier risks:

  • Premature loading before concrete gains adequate strength.
  • Deflection and sagging of the beam soffit.
  • Cracking at the tension zone of the beam.
  • Slab soffit (lighter load) = 3 days; Beam soffit (heavier load) = 7 days.
  • Props must be refixed immediately after striking — concrete is not fully cured yet.