Engineering Materials·MCQ explained

For concreting tunnel linings, transportation of concrete is done by:

Try it first: pick an option, then read the explanation.

Correct answer: D. Pumps

Detailed Explanation: Pump Transport for Tunnel Lining Concrete

Why D (Pumps) is correct: Tunnel lining presents unique challenges: the work face is deep underground, access is limited to one opening, the lining geometry is curved (arch), and concrete must often be placed overhead. Conventional transport (pans, wheel barrows) is impossible or highly impractical. Concrete pumps are the standard solution — they push concrete through rigid or flexible pipes of 100–200 mm diameter directly to the placement point.

Pump Concrete (Pumpcrete) Specifications

ParameterValue
Slump requirement80–100 mm (medium workability)
Max. horizontal distanceUp to 400 m
Max. vertical heightUp to 80 m (horizontal) / 50 m (vertical, depending on source)
Pipe diameter100–200 mm
Pre-pump treatment1:2 cement slurry pumped first to lubricate pipes
Max. aggregate sizeOne-third of pipe diameter

Why Other Methods Fail for Tunnels

MethodWhy Unsuitable for Tunnels
Pans (head loads)Impractical in confined tunnel; overhead lining impossible
Wheel barrowsShort range only; cannot reach overhead arch sections
Containers / bucketsRequire crane headroom; not available inside a tunnel
PumpsCan reach any point via flexible pipe; handles overhead placement
  • Tunnel lining concrete is placed by pumps through 100–200 mm diameter pipes.
  • Pump concrete requires slump of 80–100 mm for flowability through pipes without segregation.
  • Pipe joints must be leak-proof; max aggregate size ≤ 1/3 of pipe diameter.