For concreting tunnel linings, transportation of concrete is done by which of the following?

For concreting tunnel linings, transportation of concrete is done by:

A. Pans
B. Wheel barrows
C. Containers
D. Pumps
Correct Answer: D. Pumps

📚 Detailed Explanation: Pump Transport for Tunnel Lining Concrete

Why D (Pumps) is correct: Tunnel lining presents unique challenges: the work face is deep underground, access is limited to one opening, the lining geometry is curved (arch), and concrete must often be placed overhead. Conventional transport (pans, wheel barrows) is impossible or highly impractical. Concrete pumps are the standard solution — they push concrete through rigid or flexible pipes of 100–200 mm diameter directly to the placement point.

Pump Concrete (Pumpcrete) Specifications

Parameter Value
Slump requirement 80–100 mm (medium workability)
Max. horizontal distance Up to 400 m
Max. vertical height Up to 80 m (horizontal) / 50 m (vertical, depending on source)
Pipe diameter 100–200 mm
Pre-pump treatment 1:2 cement slurry pumped first to lubricate pipes
Max. aggregate size One-third of pipe diameter

Why Other Methods Fail for Tunnels

Method Why Unsuitable for Tunnels
Pans (head loads) Impractical in confined tunnel; overhead lining impossible
Wheel barrows Short range only; cannot reach overhead arch sections
Containers / buckets Require crane headroom; not available inside a tunnel
Pumps Can reach any point via flexible pipe; handles overhead placement
  • Tunnel lining concrete is placed by pumps through 100–200 mm diameter pipes.
  • Pump concrete requires slump of 80–100 mm for flowability through pipes without segregation.
  • Pipe joints must be leak-proof; max aggregate size ≤ 1/3 of pipe diameter.

← Back to MCQs on Concrete Operations

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top