Engineering Materials·MCQ explained

Which of the following methods explains the process of underwater concreting? (i) Pumping technique (ii) Hydro valve method (iii) Toggle bags method (iv) Bagged concrete method

Try it first: pick an option, then read the explanation.

Correct answer: C. (i), (ii), (iii), and (iv)

Detailed Explanation: All Four Methods Are Used for Underwater Concreting

Why C [(i), (ii), (iii), and (iv)] is correct: Underwater concreting is a specialised operation required for bridge piers, marine foundations, dams, and retaining walls in water. Multiple methods have been developed. All four listed methods — pumping, hydro valve, toggle bags, and bagged concrete — are recognised techniques for placing concrete underwater. The tremie method is also widely used (most common) but was not listed as one of the four options.

Underwater Concreting Methods

MethodPrincipleApplication
(i) Pumping techniqueConcrete pumped through a pipe (bottom discharge) from surface; pipe submerged with outlet kept below concrete surface to prevent water mixing; combined with tremie principle for anti-washoutLarge marine foundations; bridge caissons; modern preferred method
(ii) Hydro valve methodSpecially designed valve at bottom of concrete container allows concrete to be released underwater in a controlled manner, preventing water intrusion by hydrostatic pressure differentialShaft foundations; enclosed cofferdam pours
(iii) Toggle bags methodCanvas or jute bags (toggle bags) filled with semi-dry concrete are lowered on a rope and placed manually by divers; bags are slit or opened at the placement location; concrete flows out and knits togetherSmall repairs; inaccessible underwater locations; cofferdam sealing
(iv) Bagged concrete methodPermeable fabric bags filled with dry or semi-dry concrete are stacked or placed by divers/crane; seawater saturates the mix and initiates hydration; bags degrade leaving a consolidated massScour protection; gabion-like revetment; emergency repairs
Tremie method (most common)Steel tube (tremie pipe, φ200–300mm) lowered to base; concrete fed by gravity; pipe kept submerged in fresh concrete; raised as pour proceeds; never withdrawn from concrete surfaceBridge piers; caissons; bored pile foundations; most widely used underwater concreting method

Requirements for Concrete Mix Used Underwater

PropertyRequirementReason
w/c ratio0.4–0.55Flowable but not segregating; anti-washout
Slump150–200 mm (very high)Self-levelling without vibration (vibration causes washout)
Cement contentMinimum 400 kg/m³Rich mix for cohesion and impermeability
Anti-washout admixtureOften used in modern practicePrevents cement and fines from washing away in water
VibrationNone (or minimal)Vibration disperses concrete and causes washout
  • All four methods — pumping, hydro valve, toggle bags, and bagged concrete — are valid underwater concreting techniques.
  • The Tremie method is the most common and preferred method for large underwater pours.
  • Key principle in all methods: concrete must not fall freely through water — it must be placed in one continuous mass to prevent washout and segregation.