On which of the following does the correct proportion of ingredients of concrete depend upon?

On which of the following does the correct proportion of ingredients of concrete depend upon?

A. Bulking of sand
B. Water content
C. Absorption and workability
D. All options are correct
Correct Answer: D. All options are correct

📚 Detailed Explanation: Factors Affecting Concrete Mix Proportions

Why D (All options correct) is correct: The mix proportions must account for all three factors:
A — Bulking of sand: In volume batching, moist sand bulks by up to 30%. The measured volume must be corrected to deliver the intended dry sand quantity.
B — Water content: The primary variable in mix design; controls w/c ratio (strength), workability, and durability.
C — Absorption and workability: Aggregate absorption affects free water available (absorbed water is “locked up” and doesn't contribute to paste fluidity); required workability sets the target water content.

How Each Factor Affects Proportioning

Factor Effect on Proportioning
Bulking of sand Requires increased measured volume to deliver correct dry weight
Water content Sets w/c ratio; primary determinant of strength and workability
Aggregate absorption Absorbed water reduces free water; must be corrected in water content calculation
Required workability Determines minimum water content needed for placement
  • All three factors — bulking, water content, and absorption/workability — must be considered for correct proportioning.