Concrete is generally placed on a:

Concrete is generally placed on a:

A. Form work
B. Stand
C. Mould
D. Platform
Correct Answer: A. Form work

📚 Detailed Explanation: Concrete Is Placed on Formwork

Why A (Form work) is correct: Formwork (also called shuttering) is the temporary framework, mould, or enclosure built to hold fresh (plastic) concrete in its desired shape until it hardens and gains sufficient strength. It is the standard term used in construction for the surface on and into which concrete is poured and compacted.

What Is Formwork?

Aspect Detail
Definition Temporary structure that holds fresh concrete in shape while it cures
Materials used Timber, plywood, steel, aluminium, fiberglass, fabric
Purpose Defines shape, contains concrete, supports weight until strength develops
Cost Typically 20–25% of total concrete construction cost
Watertightness Timber formwork uses tongue-and-groove joints to prevent cement slurry leakage

Why the Other Options Are Wrong

Option Verdict Reason
A. Form work Correct Standard term for the mould/shuttering that receives fresh concrete
B. Stand Wrong Not a construction term for this purpose
C. Mould Partly correct Used for precast elements in factories, not for in-situ construction; “formwork” is the correct term for site work
D. Platform Wrong A platform is a working surface for labourers, not a mould for concrete
  • Formwork = the correct answer; it is the fundamental temporary structure for in-situ concrete construction.
  • Shuttering = another name for formwork, used interchangeably in Indian construction practice.