Engineering Materials·MCQ explained

To estimate 28-day strength from 7-day compressive strength of OPC concrete, the 7-day value should be multiplied by:

Try it first: pick an option, then read the explanation.

Correct answer: C. 1.5

Detailed Explanation: 28-day Strength = 7-day Strength × 1.5

Why C (1.5) is correct: The 7-day strength is approximately 65% of the 28-day strength (ratio 0.65). Rearranging: f28 = f7 / 0.65 = f7 × 1.538 ≈ 1.5. This multiplication factor of 1.5 is a widely used site approximation in IS codes and field practice. Derivation: f7 / f28 = 0.65 f28 = f7 / 0.65 f28 = f7 x 1.538 f28 ≈ f7 x 1.5 Worked Example (M25 concrete, site test): 7-day cube strength (f7) = 18 N/mm² (average of 3 cubes) Predicted f28 = 18 x 1.5 = 27 N/mm² Required f28 for M25 = 25 N/mm² (fck) Result: OK, as predicted f28 exceeds fck

Standard Site Decision Matrix

7-day Cube ResultPredicted 28-day (x 1.5)Decision for M25
18 N/mm²27 N/mm²Proceed — above 25 MPa
17 N/mm²25.5 N/mm²Borderline — close monitoring required
15 N/mm²22.5 N/mm²Investigate — below required 28-day strength
12 N/mm²18 N/mm²Reject or investigate materials/mix proportions

Multipliers for Different Cements

Cement Typef7/f28 RatioMultiplier (f28 = f7 × ?)
OPC (Ordinary Portland)0.65× 1.5
PPC (Portland Pozzolana)0.55–0.60× 1.65–1.80
RHPC (Rapid Hardening)0.75–0.80× 1.25–1.33
  • For OPC concrete, multiply 7-day strength by 1.5 to estimate 28-day strength.
  • This is a site approximation only — for structural decisions, always test actual 28-day cubes.
  • IS 456:2000 acceptance criterion is based on 28-day cube tests (150 mm cubes per IS 516).