Under normal conditions using an ordinary cement the period of removal of the form work is:

Under normal conditions using ordinary Portland cement, the period of removal of the form work is:

A. 7 days for beam soffits
B. 14 days for bottom slabs of spans 4.6 m and more
C. 21 days for bottom beams over 6 m spans
D. All options are correct
Correct Answer: D. All options are correct

📚 Detailed Explanation: Verifying All Three Stripping Time Statements

Why D (All options correct) is correct: Each statement maps directly to a row in the IS 456:2000 formwork stripping table for Ordinary Portland Cement.

IS 456:2000 Reference Table

S.No. Type of Formwork OPC (Minimum Period) RHC (Minimum Period)
1 Vertical formwork to columns, walls, beams 16–24 hours 12 hours
2 Soffit formwork to slabs (props refixed immediately) 3 days 2 days
3 Soffit formwork to beams (props refixed immediately) 7 days 5 days
4a Props to slabs: spanning up to 4.5 m 7 days 5 days
4b Props to slabs: spanning over 4.5 m 14 days 10 days
5a Props to beams and arches: spanning up to 6 m 14 days 10 days
5b Props to beams and arches: spanning over 6 m 21 days 14 days

Verification of Each Statement

Statement IS 456 Reference Verdict
A. 7 days for beam soffits Row 3: Soffit formwork to beams = 7 days (OPC) Correct
B. 14 days for slabs spanning 4.6 m and more Row 4b: Props to slabs spanning over 4.5 m = 14 days Correct
C. 21 days for beams over 6 m spans Row 5b: Props to beams spanning over 6 m = 21 days Correct
  • Longer spans require longer curing before prop removal because the bending moment (and thus required concrete strength) is greater.
  • All three values apply to OPC under normal conditions. Rapid Hardening Cement allows earlier striking.

← Back to MCQs on Form Work

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top